How do I calculate a fabric shortage before a production order is due?

Subtract reservations and separate quality holds from fabric on hand. Add confirmed receipts due on or before the need-by date. Compare that supply with demand in the same unit. Any positive gap is the shortage. If supply covers demand, the shortage is zero.

Fabric balance for fictional order SO-17

In Bismion’s fictional Factory A example, order SO-17 is 50 m short of the 300 m of cotton twill needed by 24 November 2026. The factory has 130 m of usable stock. Confirmed Receipt-42 brings 120 m that day, making 250 m available.

Factory A · SO-17 · 24 November 2026
EvidenceQuantityHow it counts
Stock on hand200 mStarting balance at the factory
Reserved stock50 mAlready committed to other demand
Quality hold20 mHeld separately from reservations
Usable stock130 m200 − 50 − 20
Receipt-42120 mConfirmed incoming by 24 November 2026
Available by need date250 m130 + 120
Order requirement300 mNeeded for SO-17
Shortage50 m300 − 250

What changes the answer?

If the receipt arrives a day late

A delivery on 25 November 2026 falls outside the order’s window. With 0 m incoming by 24 November 2026, the order is 170 m short.

If the receipt has no unit

Shortage unknown. Receipt-42 has no unit. Check its source unit before adding it to the fabric balance.